Old 8/2/07, 2:13 PM
Dennis R. Goudreau Dennis R. Goudreau is offline
InterNACHI Member
 
Join Date: Jun 2007
Location: Nashua, NH
Posts: 2,074
Default need opoinions /advice

put in a concrete drive way approx 6 years ago at my house, suffice to say it is now in bad shape, I would like to overlay with hot top is this a good idea or is it better to tear it out & start over thanks in advance
Reply With Quote
  #2  
Old 8/2/07, 2:20 PM
Peter C. Russell's Avatar
Peter C. Russell Peter C. Russell is offline
InterNACHI Member
 
Join Date: Jul 2004
Location: Alton Bay NH
Posts: 3,998
Default Re: need opoinions /advice

Dennis, I would think you would have to remove it. My thought is if water gets in there and freezes it will heave the new asphalt and crack it.
Reply With Quote
  #3  
Old 8/2/07, 4:03 PM
Frank M. Carrio, CMI's Avatar
Frank M. Carrio, CMI Frank M. Carrio, CMI is offline
ESOP Committee Member
 
Join Date: Jan 2004
Posts: 4,364
Default Re: need opoinions /advice

Quote:
Originally Posted by dgoudreau
put in a concrete drive way approx 6 years ago at my house, suffice to say it is now in bad shape, I would like to overlay with hot top is this a good idea or is it better to tear it out & start over thanks in advance
Hi Dennis,
A concrete driveway should have lasted you for many, many years. Sounds to me like the "base" was not stable enough, deep enough, compacted enough, or too much "expansive soil" was in the base instead of rocks and or compacted gravel.

This situation will have to be corrected/rectified or you will just have another unstable driveway on your hands. Giving unstable concrete a coating of asphalt will only exacerbate the situation and it will be money thrown down the drain.

My recommendation is complete removal of the concrete, and having a good four to 6 inches of rock/gravel compacted into a nice tight firm base.

If you decide to re-install concrete have a minimum of 3,000 PSI, 4 inches thick, with the appropriate welded wire mesh in the concrete.

Good luck!



Signed, Frank Carrio, CMI
Certified Master Inspector & Consultant
Certified Commercial Building Inspector
Certified, WDI Inspector
Founder & Current President, New Hampshire State Chapter NACHI
NACHI, State Representative for Legislative Affairs
Retired: ICC Certified Member
Retired: Code Compliance Inspector.
Retired: ASTM Committee Member
New Hampshire License #0096
Reply With Quote
Reply

Thread Tools

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On



All times are GMT -4. The time now is 6:15 PM.


Popular Sections

:

All Sections

Inspection News

InterNACHI Membership

Inspection Standards

Inspection Education

InterNACHI Inspectors

Inspection Links

 

 

 

NACHI.ORG Statistics

 

 

no new posts