I do not have much experience with 3 phase supply and wondering if I could get some answers here. Lateral supply, there is a main shutoff in the basement before the meter which is on the first floor.Then there is another shutoff after the meter. Is this normal for a three phase supply? why have a shut off before the meter?
Attached Thumbnails
3-phase-supply-question-127.jpg   3-phase-supply-question-102.jpg   3-phase-supply-question-107.jpg  



David

InterNACHI #08051301
NYS Lic. #16000038229
NYS DEC Cert # T4865884
518-505-8305
HouseAbout Home Inspections
HouseAbout on Facebook
NY Capital Region Chapter InterNACHI


Reply With Quote
Need a home inspection in Pennsylvania? Check out InterNACHI's listing of Pennsylvania certified home inspectors. Or, find a home inspector anywhere in the world with our inspection search engine.
  #2  
Old 1/10/12, 5:31 PM
David P. OKeefe's Avatar
David P. OKeefe David P. OKeefe is offline
InterNACHI Member
 
Join Date: May 2008
Location: Delmar,, NY
Posts: 974
Default Re: 3 phase supply question

Also the wiring was exposed before the panels in the basement. A cover should be on this right?
Attached Thumbnails
3-phase-supply-question-130.jpg  



David

InterNACHI #08051301
NYS Lic. #16000038229
NYS DEC Cert # T4865884
518-505-8305
HouseAbout Home Inspections
HouseAbout on Facebook
NY Capital Region Chapter InterNACHI


Reply With Quote
  #3  
Old 1/11/12, 11:03 AM
David P. OKeefe's Avatar
David P. OKeefe David P. OKeefe is offline
InterNACHI Member
 
Join Date: May 2008
Location: Delmar,, NY
Posts: 974
Default Re: 3 phase supply question

Bump, thanks Barry



David

InterNACHI #08051301
NYS Lic. #16000038229
NYS DEC Cert # T4865884
518-505-8305
HouseAbout Home Inspections
HouseAbout on Facebook
NY Capital Region Chapter InterNACHI


Reply With Quote
  #4  
Old 1/11/12, 5:57 PM
Jim Port Jim Port is offline
Unmoderated Guest
 
Join Date: Jul 2007
Location: Maryland
Posts: 805
Please Note: Jim Port is a non-member guest and is in no way affiliated with InterNACHI or its members.
Default Re: 3 phase supply question

Some utilities want a means of disconnect before the meter.

The pull box should have a cover.
Reply With Quote
  #5  
Old 1/11/12, 9:11 PM
Paul W. Abernathy Paul W. Abernathy is offline
InterNACHI Member
 
Join Date: Sep 2005
Location: Spotsylvania, VA
Posts: 8,072
Send a message via AIM to pabernathy Send a message via MSN to pabernathy Send a message via Skype™ to pabernathy
Default Re: 3 phase supply question

As Jim Stated, In many areas the Poco will want this "Meter Disconnect Switches" installed so as to me able to shut off power before the removal of the meter. Keep in mind that the SCCR rating of that "MDS" is to be equal or greater than the available short-circuit current as well as being rated to interrupt the loads served. But alas this usually taken care of by the Municipal Inspector....but it could be missed and since you're doing commercial inspections...it can be a safety issue.



Paul W. Abernathy
Reply With Quote
  #6  
Old 1/12/12, 8:17 AM
Joseph M. Whitt Joseph M. Whitt is offline
InterNACHI Member
 
Join Date: Oct 2008
Location: NC
Posts: 123
Default Re: 3 phase supply question

Not being able to see the entire installation I have several questions that come to mind by the three pictures.

Picture one seems to be the service disconnect as this is where the grounding electrode conductors are installed. The neutral conductors need to be identified by white markings.

Picture two has flexible metal conduit either supplying the meter of leaving the meter. If this is ahead of the service disconnect it is restricted to a length of no more than 6 feet.

Picture three I can’t tell if the neutral is isolated from the enclosure. If this disconnect is downstream of the service disconnect the neutral must be isolated.

Many questions abound in my mind that needs to be answered before I could give a definite answer as far as code compliance or the safety of the installation.

Many issues concerning the strapping of cables and raceways abound in picture two.



Mike Whitt
Contractor/Instructor
Reply With Quote
Reply

Thread Tools

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Duct Work insulation question Rick Vollmer Inspecting HVAC Systems 9 4/16/09 8:05 PM
Anyone Done a Phase Inspection Under the New SOP? cevans Texas/TPREIA Inspectors 8 3/3/09 12:49 PM
Sump Pit/Pump Question Joey D'Adamo Plumbing Inspections 4 11/26/08 1:04 PM
What's this video worth? jtedesco1 Inspection Education & Training 5 4/18/08 9:24 AM
Plumbing vent Routing Question kweiss Plumbing Inspections 7 11/1/06 9:57 PM


All times are GMT -4. The time now is 5:19 AM.


Popular Sections

:

All Sections

Inspection News

InterNACHI Membership

Inspection Standards

Inspection Education

InterNACHI Inspectors

Inspection Links

 

 

 

NACHI.ORG Statistics

 

 

no new posts