200amp meter base. 4/0 alum service to Bulldog "Push-o-matic" panel. Two buss bars in the panel that had 100amp breakers one each side. (One on the left, one on the right.) Question: Is the structure limited to 100amps or do we combine the two buss bars for 200amp service?
Thanks for anyones input. Peter Doane Realty Check Inspection Service NACHI ID# 05120681
|
|
#2
|
|||
|
|||
|
Peter,
Does the 4/0 conductor terminate in a common LUG for both buss bars? If so...based on the 4/0AL I would call it a 200A Service.....if it is as stated above.....both bars give the panel a capacity of 100A each...and the overall rating is 200A..... Did the panel itself have a rating on it? Paul W. Abernathy |
|
#3
|
||||
|
||||
|
Yes, the 4/0 service was at a common lug. then it split into two rows of breakers with the 100amp breakers at the top.. So 200amp is correct then?
Peter Doane Realty Check Inspection Service NACHI ID# 05120681
|
|
#4
|
|||
|
|||
|
Yes...that is correct !
Paul W. Abernathy |
![]() |
| Thread Tools | |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Arching Causes Main Breaker To Trip? | msylvester | Electrical Inspections | 10 | 10/22/07 3:57 PM |
| Double pole breaker, metal showing between sections | lfoster | Electrical Inspections | 2 | 9/6/07 12:25 PM |
| Double tap at main lugs | gmathias | Electrical Inspections | 4 | 8/8/07 7:20 PM |
| Double Tapped Breaker | tjohnson3 | Electrical Inspections | 8 | 4/20/07 9:04 AM |
| Bad electrical problem | Pest Guy | Electrical Inspections | 4 | 1/20/06 9:26 PM |