Need some help with a service disconnect. Is a handle tie required for the two outside breakers? The hot lines feed the bus bar on each side. and the wiring is such that one line to each unit is tied to the center breaker which has the handle tie?
|
| Need a home inspection in Idaho? Check out InterNACHI's listing of Idaho certified home inspectors. Or, find a home inspector anywhere in the world with our inspection search engine. |
|
#2
|
|||
|
|||
|
Please Note:
Jim Port is a non-member guest and is in no way affiliated with InterNACHI or its members.
I don't understand what is going on in that box. The disconnect would only need to be a 2 pole. What are the outside poles feeding?
|
|
#3
|
|||
|
|||
|
there are 2 units, one unit is connected to an outside breaker and on side of the double pole breaker in the middle. The other unit is connected the remaining outside breaker and the other side of the middle breaker.
|
|
#4
|
|||
|
|||
|
Please Note:
Jim Port is a non-member guest and is in no way affiliated with InterNACHI or its members.
In that case both legs would need to be disconnected at the same time. The easy solution would be to use 2 two pole breakers. The existing breaker would need to go left or right one space.
Correction, with this panel, shifting the breaker would not work. Last edited by Jim Port; 7/16/11 at 9:59 AM.. |
|
#5
|
|||
|
|||
|
Yes but that would put both lines feeding the heat pump on one incoming line. do they need to be on alternate incoming lines to be in phase?
The blue wires are for a power company load control |
|
#6
|
||||
|
||||
|
The blue wires were also double tapping the connections. Which should be corrected. A wire nut and pig tail would correct the issue. As for the connecting bar, I would think it should not matter if the wires are sized properly. All panels work this way so installing two breakers side by side should be fine. The tie bar may prevent tripping if it interferes with the center breaker.
Infraspection Institute Level 1 Certified Infrared Thermographer Fogarty Inspection Services Group of Knoxville TN Home inspections, Commercial Inspections, Thermal Imaging, Mold, Enviromental Testing and Radon Testing for Knoxville TN, Oak Ridge TN, Maryville, Clinton, Farragut, Lenoir City, Pigeon Forge, Sevierville and all the surrounding areas. 865-256-5397 www.homeinspectorknoxville.com www.moldandradon.com www.thermal-inspection.net www.commercial-building-inspector.net |
|
#7
|
|||
|
|||
|
The Homeowner call an electrican. They said the breakers could not be moved over one position and installed a new box, problem solved.
|
![]() |
| Thread Tools | |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Radiant ceiling heat? | bmargiotti | Inspecting HVAC Systems | 16 | 1/24/12 10:46 AM |
| Need Heat Pump advice | jfunderburk | Inspecting HVAC Systems | 6 | 2/5/09 10:41 AM |
| York Heat Pump | Summer House | Inspecting HVAC Systems | 7 | 2/21/07 9:13 PM |