Default leaning precast foundation walls

I have 10 foot precast foundation walls on my log home. I started the finishing process in the basement and noticed my walls are leaning about two inches in 10 feet. One wall is out and the adjacent wall is in. I backfilled per specs with gravel and half the foundation is exposed. There is no evidence of moving in the hardwood floors above and no cracks in drywall. I am concerned ragarding the structural integrity of my home. I have precast company coming for a meeting, any advice.
Reply With Quote
Need a home inspection in New Hampshire? Check out InterNACHI's listing of New Hampshire certified home inspectors. Or, find a home inspector anywhere in the world with our inspection search engine.
  #2  
Old 6/10/10, 2:11 AM
Dale Duffy's Avatar
Dale Duffy Dale Duffy is offline
InterNACHI Member
 
Join Date: Oct 2005
Location: Scottsdale, AZ
Posts: 8,261
Default Re: leaning precast foundation walls

[QUOTE=Unregistered;661046]I have 10 foot precast foundation walls on my log home. I started the finishing process in the basement and noticed my walls are leaning about two inches in 10 feet. One wall is out and the adjacent wall is in. I backfilled per specs with gravel and half the foundation is exposed. There is no evidence of moving in the hardwood floors above and no cracks in drywall. I am concerned ragarding the structural integrity of my home. I have precast company coming for a meeting, any advice.[/QUOTE]

Was the Foundation leaning before the backfill process?

Or after you began the backfilling?

Regardless, have them make it right, unless you made the Foundation out of plumb backfilling it which is a possibility.

Were braces attached to the foundation to floor before the backfilling began?...steel or wood bracing?

Or did you have a completely built house with a completely exposed Foundation, which does not make sense ..regarding your comment about the floor and drywall...or was it a Modular Home?
Reply With Quote
  #3  
Old 6/13/10, 8:02 AM
Brian A. MacNeish Brian A. MacNeish is offline
Banned
 
Join Date: Apr 2007
Location: CANADA
Posts: 4,638
Please Note: Brian A. MacNeish is a non-member guest and is in no way affiliated with InterNACHI or its members.
Default Re: leaning precast foundation walls

[QUOTE=Unregistered;661046]I have 10 foot precast foundation walls on my log home. I started the finishing process in the basement and noticed my walls are leaning about two inches in 10 feet. One wall is out and the adjacent wall is in. I backfilled per specs with gravel and half the foundation is exposed. There is no evidence of moving in the hardwood floors above and no cracks in drywall. I am concerned ragarding the structural integrity of my home. I have precast company coming for a meeting, any advice.[/QUOTE]

Was the first floor framing/subfloor in place at the time of the backfill and was the framing (sill plate/sill) properly attached to the foundation (adequate anchor bolts with washers/nuts installed)?
Reply With Quote
  #4  
Old 6/20/10, 11:03 AM
Unregistered
Guest
 
Posts: n/a
Please Note: is a non-member guest and is in no way affiliated with InterNACHI or its members.
Default Re: leaning precast foundation walls

[QUOTE=Brian A. MacNeish;662432]Was the first floor framing/subfloor in place at the time of the backfill and was the framing (sill plate/sill) properly attached to the foundation (adequate anchor bolts with washers/nuts installed)?[/QUOTE]

Please reply after the contractor that did foundation replys to his or her investigation.
It is not good to have that amount of slope and for sure some thing was out of plumb at the start or during backfill.
If it happened after backfill there will be evidence showing stress marks on wall that intersect with corners and you should examine carefully.Look at 90 dagree for stress re-bar showing there will be evidence showing you what happened and maybe even during the pour ,if it was done to fast and cement did not have time to harden to allow the pour to move up slowly.There is a time rate at witch you advance your pour for pre-cast ,insulated cells.
Please do not take this lightly for it is your FOUNDATION of the home.
Reply With Quote
Reply

Thread Tools



All times are GMT -4. The time now is 5:53 PM.

no new posts

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163 164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183 184 185 186 187 188 189 190 191 192 193 194 195 196 197 198 199 200 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215 216 217 218 219 220 221 222 223 224 225 226 227 228 229 230 231 232 233 234 235 236 237 238 239 240 241 242 243 244 245 246 247 248 249 250 251 252 253 254 255 256 257 258 259 260 261 262 263 264 265 266 267 268 269 270 271 272 273 274 275 276 277 278 279 280 281 282